Construction of a New Wastewater Lift Station - Centerport South Regional Water

Status Awarded

Solicitation number 301-2024

Publication date

Contract award date

Contract value

CAD 12,736,111.00

    Description
    This contract was awarded to:
    J-CON Civil LTD
    D4.          SCOPE OF WORK

    D4.1        The Work to be done under the Contract shall consist of the construction of a new dry well/wet well type wastewater pumping station complete with a backup generator and other site amenities. The complete Scope of Work is described in the Drawings and Specifications.

    D4.2        The major components of the Work are as follows:
    (a)   Shaft construction to accommodate the Work associated with this project.
    (b)   Connection of a new 1200 mm PVC sewer to a sewer installed by the interceptor construction team (Contract 3) at the property line of the lift station site.
    (c)    A new 3.65 m diameter precast concrete wet well to receive the wastewater from the sewer.
    (d)   A new 3.65 m diameter Fibreglass Reinforced Plastic (FRP) dry well complete with pumps, valves, access platforms, sump, sump pump, motors and other appurtenances to pump the flow from the wet well to the valve chamber.
    (e)   A cast in place concrete valve chamber complete with valving and other appurtenance to allow for flow routing to a 450 mm force main.
    (f)    Approximately 60 m of 450 mm force main that is to connect to a force main system to be installed by the force main construction team (Contract 2A).
    (g)   A 8.3 m X 8.3 m superstructure above the dry well to house electrical and mechanical equipment.
    (h)   A propane fuelled backup generator, vaporizer and propane tank to provide backup power to the lift station and superstructure.
    (i)     Raising of the existing site between 1.5 to 2 m using imported fill and installation of 
    gabion walls on the east and west sides of the project site.
    (j)     Providing a gravel driving surface for the site.
    (k)    A water cistern to provide wash down/site usage water to the superstructure.
    (l)     All electrical and mechanical works needed for a fully functional dry well/wet well lift station.
    (m)  Land drainage sewer and catch basins to provide site drainage.

    D4.3        The following shall apply to the Services:
    (a)   City of Winnipeg Green Building Policy: New City-Owned Buildings and major additions; http://clkapps.winnipeg.ca/DMIS/DocExt/ViewDoc.asp?DocumentTypeId=2&DocId=5989
    (b)   Universal Design Policyhttp://clkapps.winnipeg.ca/DMIS/DocExt/ViewDoc.asp?DocumentTypeId=2&DocId=3604
     
    Business address
    1127 Redonda St
    Sunnyside, Manitoba, R5R 0E7
    Canada
    Procurement method
    Competitive – Open Bidding
    Language(s)
    English

    Contract duration

    The contract will be for a period of 20 month(s), from 2024/10/08 to 2026/06/15.

    Trade agreements

    • North American Free Trade Agreement (NAFTA)
    • Canadian Free Trade Agreement (CFTA)
    • Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
    Contact information

    Contracting organization

    Organization
    The City of Winnipeg
    Address
    185 King Street
    Winnipeg, Manitoba, R3B 1J1
    Canada
    Contracting authority
    Drew Murray
    Phone
    204-986-2492
    Email
    DMurray@winnipeg.ca
    Date modified: