Launchway Reconstruction - Long Cove, NL
Status Awarded
Contract number F5211-190220
Solicitation number F5211-190220
Publication date
Contract award date
Contract value
Status Awarded
Contract number F5211-190220
Solicitation number F5211-190220
Publication date
Contract award date
Contract value
DELIVERABLES / SCOPE OF WORK
The scope of work for this project consists of the furnishing of all plant, labour, equipment and material for launchway reconstruction at Long Cove, NL in strict accordance with specifications and accompanying drawings and subject to all terms and conditions of the Contract.
In general, the work under this contract will consist of, but will not necessarily be limited to, the following:
.1 Demolition of the existing launchway and slipway as noted on the drawings.
.2 Supply and installation of a new concrete launchway with precast concrete panels atop cribwork, as indicated on the drawings.
.3 Supply and installation of concrete slab on grade at the approach to the launchway.
.4 Supply and installation of treated dimension timber coping, wheelguard and wheelguard blocking, as noted on the drawings.
.5 Supply and installation of rock and gravel fill, granular material and rip rap, as indicated on the drawings.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
Contractors, bidders, or those they invite to site are to review specification Section 01 35 29 – Health and Safety Requirements before visiting site. Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.
Refer to the description above for full details.