Steel Pipe Breakwater Demolition and Disposal, Port Edward, BC
Status Awarded
Contract number 4500013626
Solicitation number 300001267
Publication date
Contract award date
Contract value
Status Awarded
Contract number 4500013626
Solicitation number 300001267
Publication date
Contract award date
Contract value
The scope of work for this project consists of disposal of 512m long 914mm diameter steel pipe breakwater filled with Styrofoam. In addition, the scope encompasses any labour, transport, demolition, and additional cost. This work is to be completed in strict accordance with the accompanying drawings and specifications and subject to all terms and conditions of the Contract.
In general, the work under this contract consists of, but will not necessarily be limited to, the following:
.1 Removal and Demolition of 512m long 914mm dia. Steel Pipe Breakwater filled with Styrofoam
.1 Mobilizing, and demobilizing
.2 Deconstruction of the breakwater which includes material separation, sorting, and placement in disposal bins or trucks.
.3 Materials must be sorted prior to delivery to disposal or recycling facility at an appropriate location secured by the Contractor.
.4 The Contractor must provide proof that the breakwater is being demolished and being disposed to appropriate disposal/recycling facilities.
.2 Hauling and Disposal Fee
.1 Supply of disposal bins and/or dump trucks
.2 Hauling of sorted materials to approved disposal/recycling facilities
.3 Disposal and tipping fees generated from the breakwater demolition.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense and schedule, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, site remoteness, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
Contractors, bidders, or those they invite to site are to review specification Section 01 35 29 – Health and Safety Requirements before visiting site. Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.
Refer to the description above for full details.