The scope of work for this project consists of the furnishing of all plant, labour, equipment and materials for the complete wharf and building demolition, clean-up and removal at Little Paradise, NL, in strict accordance with the accompanying drawings and specifications and subject to all terms and conditions of the Contract.
In general, the work under this contract consists of, but will not necessarily be limited to, the following:
.1 Complete demolition, clean-up, removal, and disposal of the existing wharf, community stage building, generator shed, boardwalks and other miscellaneous items, as shown on the drawings.
.2 Complete removal, clean-up and disposal of all material/debris scattered throughout the harbour (both above and below water), within the removal limits indicated on the drawings. A diving inspection report complete with underwater video to be submitted to the Departmental Representative confirming all materials have been removed within the specified limits. The diving inspection and video is the responsibility of the Contractor.
.3 Restore existing shoreline, in the footprint of the existing structures, back to its existing condition, as shown on the drawings.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense and schedule, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, site remoteness, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
Contractors, bidders, or those they invite to site are to review specification Section 01 35 28 – Health and Safety Requirements before visiting site. Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.