Wharf Protection at Middle-Bay, Lower North Shore
Status Awarded
Contract number FP802-150080
Solicitation number FP802-150080
Publication date
Contract award date
Contract value
Status Awarded
Contract number FP802-150080
Solicitation number FP802-150080
Publication date
Contract award date
Contract value
This contract was awarded to:
SCOPE OF WORK Protection Works of Middle Bay’s fishing wharf comprises, but is not limited to: 1. Supply and installation of 1-2 tm stone ; 2. The partial demolition wooden crib wharf; 3. Partial demolition and relocation of electrical and water conduits ;and 4. Supply and installation of a safety sign. Work included in this DFO project comprises the supply of all materials, labour, tools, equipment, and also protection and transport necessary to execute and finish work accordingly to specifications, in such a manner that the whole property shows uniformity.