Halifax Metering Project: Meter Installation Services
Status Awarded
Contract number 935299
Solicitation number 19-58022
Publication date
Contract award date
Contract value
Status Awarded
Contract number 935299
Solicitation number 19-58022
Publication date
Contract award date
Contract value
This contract was awarded to:
19-58022 - Halifax Metering Project: Meter Installation Services
SUMMARY OF WORK
.1 Work of this Contract comprises the installation of energy metering equipment for HVAC and electrical services and the integration of metering equipment and data to the existing EMCS in nine buildings forming part of DND’s Halifax area portfolio including:
.1 Shearwater (SH): eight buildings. .2 Willow Park (WL): one building.
.2 Owner-Supplied Products: Contractor is required to install a number of energy meters that have been pre-purchased by the Owner and will be supplied for this Project.
.3 Work Sequence: perform work in accordance with the following staging requirements.
.1 Stage 1: Pre-installation Work
.1 Perform pre-installation review in accordance with the requirements of
Section 02 22 00 – Existing Conditions Assessment and submit report.
.2 Stage 2: Coordination of Work
.1 Coordinate and perform security clearance requirements for all staff
scheduled to work on site.
.2 Submit schedules and work plan for performing work and required shutdowns
of building services.
.3 Stage 3: Metering Installation
.1 Perform installation, verification and configuration of energy meters.
.2 Provide conduits and cables to connect energy meters to EMCS and assist
EMCS Contractors with the integration of meters to each building’s EMCS.
.3 Perform final commissioning of new metering systems in coordination with
EMCS Contractors.
.4 Stage 4: Project Closeout
.1 Submit closeout documentation.
.2 Provide training and demonstration.
.4 Time for Completion: initiate work within 5 days of receipt of notice of contract award and perform the work listed in each stage indicated in the Work Sequence above, within the time
stated in the following table.
Stage Time for Completion
Stage 1 – Pre-installation Work Within 10 days of receipt of notice of contract award
Stage 2 – Coordination of Work September 26th 2019
Stage 3 – Metering Installation November 15th 2019
Stage 4 – Project Closeout November 29th 2019
Refer to the description above for full details.