Construction of one (1) equipment shelter and one (1) generator building
Status Awarded
Contract number FP802-200292
Solicitation number FP802-200292
Publication date
Contract award date
Status Awarded
Contract number FP802-200292
Solicitation number FP802-200292
Publication date
Contract award date
This contract was awarded to:
Construction of One (1) Equipment Trailer and One (1) Generator Building
MCTS Site: St. Lawrence, Newfoundland & Labrador
Nature of Work:
The work covered under this project consists of all architectural, structural, mechanical and electrical work to facilitate the installation of new equipment and generator shelters for the Canadian Coast Guard.
.1Contract consists of construction of one (1) 9.75m x 3.7m equipment shelter, and one (1) 4.27m x 4.27m generator building as per these specifications and drawings.
.2The supply and installation of all mechanical and electrical equipment/systems, as indicated on the contract drawings and more particularly, specified herein.
.3The supply and installation of foundations as indicated on the contract drawings.
.4Site preparation, including site grading; services, etc. as indicated on the contract drawings.
.5The contractor is responsible for the testing of all systems in presence of Coast Guard personnel at delivery and a report of the testing results to be delivered to owner no later than ten (10) working days after completion of all the testing. Testing shall include but not be limited to:
.1Ventilation System
.2Lighting
.3Heating System
.4All alarm points back to alarm cabinet
.5Verification of electrical circuit designations
.6Verification of documentation
.7Physical inspection of equipment shelters
.6 Documentation on the system and subsystem is to be provided by the contractor. This shall include but not limited to:
.1Complete set of as-built drawings.
.2 A complete maintenance manual indicating required maintenance for all installed components, schedule and parts list.
.3A complete report on all system testing.
.7The work included in this contract is specified in the format of general specification document with specific works identified on drawings. The contractor remains responsible for the appropriation of the work between the trade, contractors, his own forces and suppliers. The Engineer will not be responsible for determination of or for providing opinion on the scope of work split between sub-contractors and trade jurisdictions.
Location of Work:
St Lawrence VHF Site
St Lawrence, Newfoundland and Labrador
Latitude: 46º 55’ 08" North
Longitude: 55º 22’ 44" West
Start Date:
Two (2) weeks after Contract Award.
Completion Date:
40% completion by March 31, 2021.
Final completion by July 16, 2021.
Refer to the description above for full details.