Harbour Improvements, Petty Harbour, NL
Status Awarded
Contract number 4500010755
Solicitation number 30000937
Publication date
Contract award date
Contract value
Status Awarded
Contract number 4500010755
Solicitation number 30000937
Publication date
Contract award date
Contract value
This contract was awarded to:
Harbour Improvements, Petty Harbour, NL
The scope of work for this project consists of the furnishing of all plant, labour, equipment and material for harbour improvements, in Petty Harbour, NL in strict accordance with specifications and accompanying drawings and subject to all terms and conditions of the Contract.
In general, the work under this contract will consist of, but will not necessarily be limited to, the following:
.1 Demolition and complete removal of a creosote timber crib slipway. Demolition and removal of a section of existing creosote timber marginal wharf, in area noted on the drawings. All creosote timber to be disposed of at the Provincial Waste Disposal Facility at Robin Hood Bay, NL.
.2 Construction of new treated timber cribwork, complete with reinforced concrete deck to the dimensions indicated on the drawings.
.3 Supply and installation of mooring cleats, structural timber for coping, wheelguard, wheelguard blocking, fenders, ladders and associated hardware for new crib construction.
.4 Uplands rock and gravel fill placement topped with granular material as noted on the drawings.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
Contractors, bidders, or those they invite to site are to review specification Section 01 35 29 – Health and Safety Requirements before visiting site. Take all appropriate safety measures for any visit to site, either before or after acceptance of bid.
Refer to the description above for full details.