Lac La Biche County - Invitation to Bid - Bold Center Road Network Infrastructure Installation (Phase 1 and Phase 2)
Solicitation number AB-2026-03654
Publication date
Closing date and time 2026/05/29 10:00 EDT
Description
SUMMARY OF WORK:
The major items of work include the following approximate quantities:
1. General requirements including mobilization, de-mobilization and survey layout etc.
2. Remove and dispose 34m of existing 200mm dia. Storm Sewer
3. Remove and dispose of 5 v.m of existing 2 Manholes including Frame and Covers
4. Remove and dispose of 1 existing Curb & Gutters
5. Remove and dispose of 3,928m3 existing Asphalt (100mm-120mm depth)
6. Remove and dispose of / re-use 7,858m3 existing GBC (up to 300mm depth; subject to site condition
and deletion)
7. Remove and dispose of 2,046m existing Curb & Gutters
8. Remove and dispose of 460m3 of existing Concrete (150mm -200mm depth; subject to site condition
and deletion)
9. Remove and dispose of / submit existing 1 Fire Hydrant
10. Relocate (un-install and re-install complete) existing 17 Light Poles (single/double head)
11. 18,486m3 topsoil and organic material stripping, hauling to the designated area (within 1.0km),
stockpiling and dispose off (300mm depth; subject to site conditions and deletion; subject to site
conditions and deletion)
12. 31,252m3 common excavation including cut, fills, compaction, hauling to the designated area (within
1.0km) and stockpiling (subject to site condition and deletion)
13. 2,928m2 of existing asphalt milling (50mm depth)
14. Supply & install 60m, 3m wide trapezoidal day light channel including Class-1 riprap, geotextile
complete; subject to site condition and deletion).
15. Supply & install new 1,230m, 300mm dia., PVC DR35 Sanitary Sewer (3m-5m depth) - shored
vertical trench
16. Supply & install 7 new, 25.2 v.m of sulfate resistance 1,200mm diameter Manholes
17. Supply & install 7 new NF-80 (floating) Manhole’s Frame & Cover c/w Final Grade Adjustment
18. Tie-in 3 connections, 300mm dia. new Sanitary Sewer to existing Manholes
19. Tie-in 7 connections, 300mm dia. new Sanitary Sewer to existing Manholes including internal drop
structure complete
20. Maintain (uninterrupted) sanitary services to all the residents throughout construction and bypass
pumping of all sanitary flows including inflow and infiltration and back up pump from start till
completion of project
21. Supply & install 31,746m3 clay complete including common excavation, cuts, fills, compaction,
hauling and stockpiling (subject to site condition and deletion)
22. Over excavation and disposal of approximately 910m3 of unsuitable material (subject to site
condition and deletion)
23. Over excavation and placement of 910m3 of Washed Rock (subject to site condition and deletion)
24. Approximately 300m of Special Foundation (1m wide, 150mm depth concrete subject to site
condition and deletion)
25. Supply & install new 1,438m of Ultra Rib Storm Sewer 525mm dia. (3m-5m depth) – shored
vertical trench
26. Supply & install new 332m of PVC Ultra X2, 750mm dia. (3m-5m depth) – shored
vertical trench
27. Supply & install new 402m of PVC Ultra X2, 900mm dia. (3m-5m depth) – shored
vertical trench
28. Supply & install 17 new, 51 v.m of sulfate resistance 1,200mm diameter Manholes
29. Supply & install 11 new, 54.2 v.m of sulfate resistance 1,500mm diameter Manholes
30. Supply & install 28 new NF-80 (floating) Manhole’s Frame & Cover c/w Final Grade Adjustment
31. Tie-in 4 connections of 525mm dia. new Storm Sewer to existing Manholes
32. Supply & install 2 new, 6.5 v.m of sulfate resistance 1,200mm diameter CB Manholes
33. Supply & install 64 new 610 CB with 250mm dia. leads complete
34. Supply & install 60m new 900mm dia., PVC Ultra X2 with steel casing pipe 1,200mm dia., 12.7mm
thick stainless steel casing, spacer BWM-R or equivalent as per manufacturer specifications
(3m - 5m depth; installed by cased boring/augering; subject to site condition and deletion)
35. Maintain (uninterrupted) stormwater / drainage throughout construction and bypass pumping of all
stormwater / drainage flows and back up pump from start till completion of project
36. Supply & install new 82m of C-900, PVC DR18 Watermain 150mm dia. (3m depth) – shored vertical
trench
37. Supply & install new 664m of C-900, PVC DR18 Watermain 300mm dia. (3m depth) – shored
vertical trench
38. Supply and install 7 new, 300mm Gate Valve c/w Valve Box complete
39. Supply and install 4 new, 150mm Gate Valve c/w Valve Box complete
40. Supply and install 9 new Fire Hydrant, Valve and Lead complete
41. Tie-in 4 service connections, 150mm dia. to existing 300mm dia. Watermain complete
42. Tie-in 2 connections, 300mm dia. new Watermain to existing and new 300mm Watermains complete
43. Supply and install 9, 50mm dia. new Flush Point with plug complete
44. Maintain (uninterrupted) water supply to all the residents throughout construction
45. Supply and install 101,790m2 new Sub-Grade Preparation (150mm depth; subject to site condition
and deletion)
46. Reuse and install 7,858m3 existing road’s Gravel Base Course (GBC; 300mm depth; subject to site
condition and deletion)
47. Supply and install 25,324m3 new Gravel Base Course (GBC; 300mm depth; subject to site condition
and deletion)
48. Supply and install 43,458m2 of Cement Stabilization (25Kg/m2/300mm)
49. Supply and install 101,790m2 of Geotextile (16oz/yd2; subject to site condition and deletion)
50. Supply and install 101,790m2 of Geogrid (subject to site condition and deletion)
51. Supply and install 59,412m2 of new Hotmix Asphalt Concrete Paving (120 mm depth; two lifts; 70mm
and 50mm; subject to site condition and deletion)
52. Supply and install all pavement markings and signage complete (according to drawings 1200, 1201,
1202 & 1203)
53. Maintain (uninterrupted) access to public and all the residents throughout construction
54. Supply and install 35 new Cobra Head / Contemporary Coach / Galleon Lights complete complete
(subject to site condition and deletion)
55. Supply and install 40m2 retaining wall as per drawing 1104
56. Supply and install new 1,045m, 1.5m wide Concrete Walk
57. Supply and install new 1,760m, 1.5m wide Concrete Monowalk
58. Supply and install new 4,690m of 150 Curb & 250mm Gutter (straight face)
59. Supply and install new 345m, 1m wide, 200mm thick V Gutter
60. Supply and install 382m2, 150mm thick Concrete (subject to site condition and deletion)
61. Supply and install 27,876m2 of new Topsoil (100 mm depth; subject to site condition and deletion)
62. Supply and install 19,512m2 Mechanical Seeding (subject to site condition and deletion)
63. Supply and install new 8,364m2 Sod (subject to site condition and deletion)
Contract duration
The estimated contract period will be 15 month(s), with a proposed start date of 2026/06/19.
Trade agreements
-
Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
Contact information
Contracting organization
- Organization
-
Lac La Biche County
- Address
-
PO Box 1679 13422 HWY 881Lac La Biche, CA-AB, T0A 2C0CA
- Contracting authority
- Dr. Amin Augustin Ph.D., P.Eng
- Email
- amin.augustin@cceab.ca
- Address
-
PO Box 1679 13422 HWY 881Lac La Biche, Alberta, T0A 2C0Canada
Bidding details
Full details for this tender opportunity are available on a third-party site
Click on the button below to be directed to this website. Note that on the third-party site you may need an account to view and/or bid on this tender. Information on any fees or additional costs to access the full details is outlined in the Description tab of this tender opportunity.