TND0022263, Asphalt Concrete Pavement, Crack Repair, Culvert Liner Installation and Other Work
Solicitation number TND0022263 - Q&A Clarifications No. 3
Publication date
Closing date and time 2023/03/14 16:01 EDT
Last amendment date
Description
Tender available date: February 9, 2023
Tender closing date: March 14, 2023
Project Inquiries: Robert Novak, Project Procurement Officer
E-mail: Robert.Novak@gov.ab.ca
TENDERS will only be received by email at trans.tender@gov.ab.ca, before 2:01:00 P.M., for construction of the following work:
TND0022263
Asphalt Concrete Pavement, Crack Repair, Culvert Liner Installation and Other Work
683:02 Hwy 744 - Hwy 2
kilometre 0.000 to 9.766
Asphalt Concrete Pavement, Cold Milling, Culvert Liner Installation and Other Work
2:60 3 km N of Hwy 683 - 6 km S of Hwy 688
kilometre 14.890 to 23.818
Drainage Improvements and Other Work
2:60 Drainage Improvements South of Nampa
kilometre 8.950 to 9.535
Drainage Improvements and Other Work
683:02 Hwy 683:02 Drainage Project
kilometre 6.281 to 6.906
Peace Region
APPROXIMATE QUANTITIES:
70 950 tonne Supply of Aggregate – With Option
1 lump sum Environmental Protection Works
15 600 cubic metres Common Excavation
14 600 square metres Geogrid – Supply and Install
284.9 metres Culverts – Remove and Dispose (C.S.P.) (over to 700 mm dia.)
480 metres Culverts – Supply and Install (800 mm dia. C.S.P.)
63 metres Smooth Wall Steel Pipe – Supply and Install (914 mm dia.)
74.6 cubic metres Grouting of Abandoned Culverts
2 320 cubic metres Asphalt Surfacing – Remove and Dispose
12 900 tonne Granular Fill (Des 2 Class 25)
11 870 tonne Granular Base Course (Des 2 Class 25)
23 600 tonne Asphalt Concrete Pavement –EPS- Mix Type H2 (PG 58-28)
660 tonne Gravel Surfacing Des. 4 Class 25
18.7 km Roadway Lines – Supping Paint and Painting (Directional Dividing and 2 Edge Lines)
23.4 km Milled Rumble Strip – Gap Edge Line
24 330 square metres Topsoil Placement
Highway 683:02 / Range Road 212 Drainage Work
1 lump sum Traffic Accommodation for Bridge Construction
1 lump sum Demolition and Disposal of Bridge Structure
500 cubic metres Excavation – Structural
0.15 ha. Clearing
4 300 cubic metres Common and/or Borrow Excavation Loaded to Trucks
180 cubic metres Heavy Rock Riprap (Class 1)
200 metres Erosion Control Barrier (Silt Fence)
Contractor to supply all materials.
This tender is subject to the requirements of the Agreement on Government Procurement (GPA). Tenders shall be submitted in English. The specified Contract Completion Date for this work is October 15, 2023.
Contract duration
The estimated contract period will be 1 month(s), with a proposed start date of 2023/02/09.
Trade agreements
-
World Trade Organization Agreement on Government Procurement (WTO GPA)
-
Canadian Free Trade Agreement (CFTA)
-
Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
-
Comprehensive and Progressive Agreement for Trans-Pacific Partnership (CPTPP)
Contact information
Contracting organization
- Organization
-
Alberta Transportation & Economic Corridors
- Address
-
4999-98 AvenueEdmonton, Alberta, T6B 2X3Canada
- Contracting authority
- Robert Novak
- Phone
- 780-6447581
- Email
- Robert.Novak@gov.ab.ca
- Address
-
Twin Atria Building 4999 - 98 AveEdmonton, Alberta, T6B 2X3Canada
Bidding details
Full details for this tender opportunity are available on a third-party site
Click on the button below to be directed to this website. Note that on the third-party site you may need an account to view and/or bid on this tender. Information on any fees or additional costs to access the full details is outlined in the Description tab of this tender opportunity.