Services Building Condition Assessments-City of Winnipeg Community Centre-Arenas
Solicitation number 570-2023
Publication date
Closing date and time 2023/09/15 13:00 EDT
Last amendment date
Description
D3. SCOPE OF SERVICES
D3.1 The Services required under this Contract shall consist of professional consulting
services for a comprehensive Building Condition Assessment (BCA) along with recommendations for
maintenance, repairs, upgrades and related construction cost estimates of nine (9) City of Winnipeg
Community Centre-Arenas in accordance with the following:
(a) Review of existing building data and maintenance history documentation for all disciplines
provided by the Project Manager and representatives from each building, site investigations,
non-destructive testing methods and meeting with facility administration and key maintenance
personnel;
(b) The Consultant shall prepare a detailed report comprised of the following components:
(i) Structural conditions, including but not limited to foundations, floors, columns,
loadbearing walls and building envelope (exterior walls, exterior door/windows, roofing structure);
(ii) Thermographic scanning of building envelope to observe temperature differentials on
building elevations with areas that are consistent with air leakage, inadequate insulation or wet
insulation;
(iii) Mechanical components, including but not limited to heating and ventilation systems,
controls, refrigeration system (Ammonia/Freon Ice Plant), de-humidification systems, domestic
hot/cold water systems, sanitary waste and vents, fire protection, generator fuel systems;
(iv) Electrical components, including but not limited to electrical distribution systems,
emergency power, general lighting, lighting controls, access control systems, fire egress signage,
fire alarm systems, elevators and/or lifts;
(v) Architectural components, including but not limited to flooring materials, interior
windows/doors, door hardware, ceilings, interior walls and millwork;
(vi) Life Safety & Accessibility, including but not limited to roof fall arrest system, fire
extinguishers, exit stairwells, change/locker rooms, washrooms, universal washrooms,
elevators/lifts, hazardous materials; and
(vii) Energy audits, including but not limited to reducing energy consumption, building utility
costs, existing peak electricity and identify strategies to move to low carbon energy sources.
(c) Further to D3.1, the consultant team is recommended to attend two (2) community centre-
arenas site investigations in order to accurately assess and document observations of existing
conditions;
(d) The nine (9) Community Centre – Arenas which are part of the RFP No. 570-2023 include the
following sites with applicable building areas and addresses:
(i) Allard Arena (30,059 sf) 80 Allard Avenue
(ii) Dakota C.C. - Sportsplex (65,843 sf) 1188 Dakota Street
(iii) Garden City C.C. - Multiplex Arena (102,047 sf) 745 Kingsbury Avenue
(iv) Gateway C.C. - Arena (55,790 sf) 1717 Gateway Road
(v) Glenwood C.C. - Arena (24,771 sf) 27 Overton Street
(vi) Maples C.C. - Multiplex (27,557 sf) 454 Adsum Drive
(vii) Richmond Kings C.C. - Arena (24,348 sf) 666 Silverstone Avenue
(viii) St. Norbert C.C. - Arena (28,097 sf) 3450 Pembina Highway
(ix) West Kildonan Memorial C.C. - Arena (25,951 sf) 346 Perth Avenue
(e) Consulting team personnel will be required to obtain and maintain Security Clearances as
identified in Part E, for the duration of the assignment;
(f) Existing asbestos containing material inventory listing and associated drawings shall be
provided to the successful bidder by the Project Manager.
(g) An estimate of the deferred maintenance and update calculations of the Facility Condition
Index (FCI), addressing existing deficiencies (maintenance needs) only;
(h) An estimate of the Requirement Index (RI) which covers a facility need or deficient
conditions that should be addressed, including deferred maintenance, grandfathered code building
issues and building equipment needs;
(i) A final draft copy of the complete detailed report is to be submitted for review and
feedback to the Project Manager and City of Winnipeg team personnel prior to the final deliverable.
D3.1.1 The Services required under D3 shall be in accordance with the City’s Project
Management Manual http://winnipeg.ca/infrastructure/asset-management-
program/templates-manuals.stm#2 and templates http://winnipeg.ca/infrastructure/asset-
management-program/templates-manuals.stm#4 . Notwithstanding the foregoing, the Consultant is being
engaged by the City for their professional expertise; the Consultant shall bring to the Project
Manager’s attention any aspect of the City’s Project Management
mplates which the Consultant is of the opinion is not consistent with good ry practice.
D3.2 PART A - BUILDING CONDITION ASSESSMENT
(a) The Consultant is to perform a comprehensive Building Condition Assessment (BCA) of the
specified buildings. Investigation shall be through visual, non-destructive site reviews and
review of all available supporting documentation (drawings, specifications, maintenance history).
The purpose of the BCA is to facilitate a better understanding of the true extent of required
upgrades of the specified buildings. Based on the age of the various buildings many building
systems and components will have exceeded their expected lifespan. This is a common reality among
the City’s building inventory. The Consultant is expected to document observed conditions and
provide informed opinions regarding a realistic remaining lifespan of all building components.
(b) The assessment shall evaluate the existing condition of Architectural, Structural, Mechanical
and Electrical components, systems and services. Note that where systems and services are shared
or interconnected with the community centre, it may be necessary to evaluate areas occupied by the
community centre.
(c) The Consultant’s personnel shall require and maintain Security Clearances as identified in
Part E, for the duration of the assignment.
(d) The content and format of the Building Condition Assessment (BCA) shall be in conformance
with ‘Protocols for Building Condition Assessment’ published by the National Research Council.
D3.3 PART B - CODE COMPLIANCE REVIEW
(a) It is understood that all applicable codes and standards have been updated and/or introduced
since the time of the facilities construction. For the purposes of this assessment, the Consultant
is to assume that the intended future major Occupancies within the facilities shall be Group A,
Division 3.
(b) The report is to provide a comprehensive assessment with respect to compliance with present
codes and standards including:
(i) Winnipeg Building Bylaw
(ii) Manitoba Building Code
(iii) National Fire Code of Canada
(iv) National Plumbing Code
(v) CSA C22.1 Canadian Electrical Code
(vi) 2015 City of Winnipeg Accessibility Design Standards (WADS)
(c) Similar to the Building Condition Assessment, the Consultant shall exercise professional
judgement and discretion in determining the feasibility of achieving compliance with current codes
or standards. The purpose of this Code Compliance Review is to identify existing conditions that
do not comply with current code(s) and the extent of upgrades required to achieve compliance. In
each case, the Consultant shall include applicable code reference(s).
(d) Compliance with the WADS applies to all City-owned and City-occupied spaces. The assessment
shall identify any shortcomings related to compliance with this standard. Compliance with WADS is
considered mandatory, and no exemptions or legacy clauses (grandfather clauses) shall apply.
Certain exemptions will be permitted where it is “technically not feasible” to comply. In such
cases, solutions based on ‘equivalent facilitation’ may be proposed (refer to 2015 CWADS: p. 25).
(e) While certain building code violations are likely to be permitted to continue under a
grandfather clause, these conditions that represent risks to occupant safety or heath must not be
ignored. Remedial work to rectify these conditions is to be described in the Facility Renewal
Plan, complete with cost estimates.
(f) For each non-compliant condition, the Consultant is to determine:
(i) The degree to which the condition represents a risk to occupant safety (if any);
(ii) Whether the condition will be permitted to remain under a legacy clause. The Consultant
will be required to provide a detailed assessment of such conditions. In cases where the Winnipeg
Building By-law is not clear, consultation and clarification with the Authority Having Jurisdiction
may be necessary;
(iii) Class 4 estimate of the cost for upgrades necessary to achieve compliance with present
code. This estimate is to be included regardless of whether a condition is likely to be permitted
under legacy clause.
D3.4 The following shall apply to the Services:
(a) Universal Design Policy
http://clkapps.winnipeg.ca/DMIS/DocExt/ViewDoc.asp?DocumentTypeId=2&DocId=3604
(b) Efficiency Manitoba Energy Audit Program - ASHRAE Level 2 or 3 audits for eligible commercial
buildings
https://efficiencymb.ca/business/commercial-energy-audit-program/.
D3.5 PART C FACILITY RENEWAL PLAN
(a) With findings from the Building Condition Assessment (Part A) and the Code Compliance Review
(Part B), the Consultant shall prepare a Facility Renewal Plan. The Plan is to include an
inventory of the building components and systems along with an indication of their respective age
and condition. The assessment for each component shall include:
(i) Installation date (if available). If unknown, indicate the approximate age of each component;
(ii) Estimated remaining service life. Beyond the date of installation and life expectancy, this estimate should be informed by the present condition and maintenance history for each component;
(iii) Anticipated cost for major repairs or maintenance. The Consultant is to identify and prioritize repairs or maintenance expenditures based on degree of importance and long-term cost/benefit evaluation. Recommendations for required repairs or maintenance work shall be categorized as follows:
(i) Short Term Recommendations (within 1-2 years) – High priority for repairs and maintenance
including mandatory work in order to comply with applicable codes, regulatory issues and standards.
(ii) Medium Term Recommendations (3-5 years) – Repairs required to address deterioration of
building components that do not present an immediate safety hazard and/or will not result in a
significant increase in deterioration if deferred.
(iii) Long Term Recommendations (5-10 years) – Repairs required to address ongoing or low-risk
deterioration, replacement of end service-life components, and/or to improve durability of the
building.
(iv) Long Term Considerations/Recommended Improvements (not time critical) – Optional work
including recommended improvements presented for future consideration and planning.
(b) Certain building upgrades will result in improved energy performance. In such instances, the
Consultant shall include an estimate of the proposed payback period for consideration.
(c) The Consultant is to exercise professional judgement in recommending the cost-effective
solutions.
D3.6 PART D - COST ESTIMATES
(a) Consultant shall prepare detailed cost estimates for proposed maintenance, repairs and
upgrades as presented in the Facility Renewal Plan.
(b) Provide separate Class 4 construction cost estimates for maintenance and repair work as
identified in Parts A and B, summarized in Part C Facility Renewal Plan (D3.5).
(c) Costs in each estimate shall be presented in current construction market pricing (without
escalation). Present this information in a Table Format, as per the attached template.
(d) All cost estimates are to be prepared by a Professional Quantity Surveyor.
(e) Class 4 Cost Estimate Classification shall be in accordance with AACE International
Recommended Practices.
(f) The Services required under D3 shall be in accordance with the City’s Project Management
Manual http://winnipeg.ca/infrastructure/asset-management- program/templats-manuals.stm#2 and
templates http://winnipeg.ca/infrastructure/asset- management-program/templates-manuals.stm#4.
Notwithstanding the foregoing, the Consultant is being engaged by the City for its professional
expertise; the Consultant shall bring to the Project Manager’s attention any aspect of the City’s
Project Management
mplates which the Consultant is of the opinion is not consistent with good industry practice.
D3.7 PART E - ENERGY AUDITS
(a) Buildings represent one of the largest sources of greenhouse gas (GHG) emissions in Winnipeg, accounting for 44.4 percent of community-wide emissions in 2022. At the corporate level, City facilities accounted for 34 percent of overall energy use and 21 percent of emissions. Most building emissions at the community-wide and corporate levels come from the use of natural gas for heating purposes.
(b) OurWinnipeg 2045 sets out the City’s climate target of net zero emissions by 2050 which aligns with federal and international targets. The Community Energy Investment Roadmap (CEIR) identifies City and community-wide systems level actions and investments to achieve this updated target. CEIR identifies that, after reducing the need for energy and increasing energy efficiency, electrification of buildings is key to meeting our climate targets. Council directed the Public Service to implement CEIR in July 2022.
(c) The main objectives of the Energy audits are to:
(i) Reduce energy consumption at the community centre arenas through various methods including arena improvements, equipment upgrades, etc.
(ii) Reduce building utility costs.
(iii) Reduce existing peak electricity demand.
(iv) Identify strategies to move to low carbon energy sources. In Manitoba this means moving
from fossil fuel usage to electricity.
(d) The Consultant is to perform an ASHRAE level 2 energy audit. The following is to be included:
(i) Facility description including, schedules, energy sources and comfort or health concerns
including indoor environmental quality (IEQ) deficiencies.
(ii) Descriptive information for the following components, but not limited to:
(iii) Building envelope
(iv) Overall enclosure tightness
(v) HVAC
(vi) Domestic hot water
(vii) Lighting (interior and exterior)
(viii) Plug loads
(ix) Monthly and annual utility data; a minimum of 12 months is required, however ideally 2-3
years of data should be analyzed.
(x) Utility rate information
(xi) Annual Energy Use Intensity and Energy Cost Index
(xii) Energy End-Use Breakdown
(xiii) Benchmarking
(xiv) Report Low-Cost and No-Cost recommendations
(xv) Report potential capital Energy Efficiency Measure (EEM) recommendations; present a
summary of the implementation cost for each measure, the approximate measure life, the simple
payback period in years and the simple Return on Investment (ROI). The payback and ROI should
include 2% escalation on both electricity and natural gas along with carbon tax with a continuation
of $170/tonne of CO2 beyond the year 2030.
(xvi) Potential energy and carbon reduction incentives and grants from corporations such as
Efficiency Manitoba and the Green Municipal Fund etc.
(e) Efficiency Manitoba offer financial incentives and technical support for building owners that
complete ASHRAE Level 2 or 3 audits for eligible commercial buildings:
https://efficiencymb.ca/business/commercial-energy-audit-program/. Where possible, please take
advantage of the Efficiency Energy Audit Program, however, please note that the energy auditor has
to be a pre-qualified Consultant and the application must be approved prior to on-site assessment
work.
(f) The City will provide a minimum of 1 year, up to 3 years of energy, demand and cost data
along with the Manitoba Hydro rate each facility falls under to the selected consultant.
(g) It is understood that currently, electricity costs more than natural gas. The City
acknowledges that transitioning to electricity may result in increased utility costs, however, the
City is keen on exploring electrification options that leverage a coefficient of performance (COP)
higher than 1 for applicable applications.
D3.8 The funds available for this Contract are $450,000.00 (MRST included, GST extra).
Bidding and Documents are available on http://www.merx.com. Fees may apply; See https://www.merx.com/public/pricing for more information.
Contract duration
The estimated contract period will be 0 month(s), with a proposed start date of 2024/01/01.
Trade agreements
-
Canadian Free Trade Agreement (CFTA)
-
Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
-
Please refer to tender description or tender documents
Contact information
Contracting organization
- Organization
-
The City of Winnipeg
- Address
-
185 King StreetWinnipeg, Manitoba, R3B 1J1Canada
- Contracting authority
- Suzanne Bird
- Phone
- 204-986-7507
- Email
- sbird@winnipeg.ca
Bidding details
Full details for this tender opportunity are available on a third-party site
Click on the button below to be directed to this website. Note that on the third-party site you may need an account to view and/or bid on this tender. Information on any fees or additional costs to access the full details is outlined in the Description tab of this tender opportunity.