SAP Ariba system maintenance

SAP Ariba will be unavailable for scheduled maintenance at the times listed below. We apologize for any inconvenience.

  • Saturday, November 23 from 7:00 pm until 11:00 pm (EST) 

CC150 POLARIS - MULTI YEAR IN-SERVICE SUPPORT CONTRACT

Solicitation number W8485-125648/B

Publication date

Closing date and time 2013/01/02 14:00 EST

Last amendment date


    Description
    Trade Agreement: NONE
    Tendering Procedures: The bidder must supply Canadian goods
    and/or services
    Attachment: None
    Competitive Procurement Strategy: Best Overall  Proposal
    Comprehensive Land Claim Agreement: No
    Nature of Requirements: 
    CC150 POLARIS - MULTI YEAR IN-SERVICE SUPPORT CONTRACT
    
    W8485-125648/B
    Chauvin, Lorraine
    Telephone No. - (819) 956-0559 
    Fax No. - (819) 997-0437
    
    
    Amendment No 008 is issued to provide an eighth and last Q&A:
    
    Question 1: There is no SOW requirement for this, but it appears
    that RCAF/DND require technicians to wear "dress uniforms" (suit
    type jackets, tie, etc) for VIP flights. Would these costs be
    included in the Line Maintenance Flat Monthly Fee?
    
    Answer 1: There is no requirement from RCAF/DND for technicians
    to wear "dress uniforms". Some contractors might provide
    uniforms for image or branding reasons. 
    
    
    Question 2: Would Canada extend the solicitation period to 4 Jan
    to provide reasonable travel options after the holidays? 
    
    Answer 2: Canada will not grant any further extensions.
    Proposals must be received at the Bid Receiving Unit (BRU) by 02
    January 2013, 2:00PM EST. Bidders may deliver their proposals
    prior to that date, and they will be accepted by the BRU.
    
    
    Question 3: Can you confirm whether the deadline to submit
    questions has officially changed, and when we can expect to
    receive final responses to submitted questions? If we plan to
    submit the bid early to avoid travelling on 1 Jan, we need to be
    assured that further questions will not be posed and answered
    that may change our proposal.
    
    Answer 3: PWGSC confirms that no question asked after COB
    Thursday 20 December 2012 will be answered. The last answers
    will be provided on 21 December 2012. Bidders may confidently
    send their bids to the PWGSC Bid Receiving Unit between
    Christmas and New Year.
    
    
    Question 4: In Appendix 3 Scoring Guide, Part B - Technical
    Point-Rated Requirements, PQA1, the Evaluation Criteria states
    "3 points will be given for the first DE and 2 points will be
    given for subs (substitutes), up to a maximum of 5 points per
    specialty area". If an individual has more than one DE
    accreditation, will credit be given for both? For example, if a
    primary DE engineer is accredited in both 'Structures' and
    'Systems - Mechanical', will 6 points be granted? 
    
    Answer 4: An individual with more than one DE accreditation will
    get credit in all his/her specialty areas. In the example above,
    6 points with be granted for this individual. Any additional DE
    in the same specialty areas will be awarded 2 points, for a
    maximum of 5 points per specialty area.
    
    
    Question 5:  In PQA1, the evaluation criteria states that "DND's
    requirement is a minimum crew of 3 qualified technicians (ACAs)
    per refueler on air-to-air missions, available 24/7, and a
    permanent state of readiness".  It is assumed that the 24/7
    availability means ready to deploy 24/7 and only 3 technicians
    deploy with the aircraft. Is this correct? Or does this mean
    available at work (on shift) 24/7 while deployed (around the
    clock work activity for 3 technicians)?
    
    Answer 5: It means both. At all times (state of readiness),
    Contractor must be ready to deploy 24/7 with a minimum crew of 3
    qualified technicians per refueler. It might be more than 3
    technicians for long term deployments, such as during Ops
    Libeccio. At the site visit, Captain Dumais confirmed that a
    team of 3 technicians could perform the work required prior to
    take-off and after landing, including repairs. More than 3
    technicians were deployed during Ops Libeccio, as we cannot
    expect the same 3 technicians to be at work 24 hours per day for
    21 days in a row.
    
    
    Question 6: Can PWGSC please confirm the version of Internet
    Explorer that will be on the computers used by the proposal
    evaluators?
    
    Answer 6: Internet Explorer 7.
    
    
    HISTORY OF PREVIOUS NPP AMENDMENTS:
    
    Amendment No 007 is issued to provide a seventh Q&A, to postpone
    the Solicitation closing date to 02 January 2013, and to advise
    bidders that inquiries received later than 20 December 2012
    might not be answered.
    
    Question: Would PWGSC agree to extend the solicitation period to
    10 January 2013?
    
    Answer: PWGSC is extending the solicitation period to 02 January
    2013 at 2:00PM EST.
    
    
    Amendment No 006 is issued to provide a sixth Q&A: 
    
    QUESTION 1: The response to a previous question about Canadian
    Content seems to indicate that, for those BOP Line Items that
    request bidder to provide a mark-up percentage, the total bid
    price calculation will not include the cost of the item, but
    will only include the actual mark-up value. Is it the
    Government's intention that the following Basis of Payment Line
    Items include the bidder's Mark-up percentage rate and the total
    value of the Mark-up amount, but not the cost of the Line Item
    plus the Mark-up amount?
    · 3.3 b), Mark-up HM subcontracted to EADS
    · 3.4, Mark-up on Aircraft Painting
    · 3.6 b), Engine Maintenance, GE O/H
    · 5.0, Mark-up on Materiel/Inventory Replenishment
    · 6.0, Mark-up on other Subcontracts
    
    ANSWER 1:  In table 2 of the BOP, the total bid price excludes
    spendings such as subcontracts to EADS, aircraft painting,
    engine maintenance, material/inventory replenishment and other
    subcontracts. The total bid price includes only the mark-up, as
    the spendings are the same for all bidders. Nevertheless, Canada
    will reimburse the contractor's laid-down cost, and pay the
    mark-up or service charge associated to the spending, plus
    applicable taxes.   
    
    
    QUESTION 2: Canada has identified that the cost of the Airbus
    MRO-CSA is to be included in flat rate for line maintenance.
    Please clarify that this is only the cost of the MRO-CSA, and
    not services resulting from it such as engineering support,
    flight permit authorization, etc.
    
    ANSWER 2: Canada confirms that the cost of services resulting
    from the Airbus MRO-CSA, such as engineering support and flight
    permit authorization, will be reimbursed under BOP Line Item
    6.0, Miscellaneous Subcontracts, plus applicable mark-up and
    taxes.
    
    
    QUESTION 3: Para 6 a) of RFP Annex A, Instructions For Technical
    Submissions, states 3 projects in last 2 years. The Scoring
    guide states 3 projects in last 5 years. This was changed prior
    to the formal RFP was put out. Please confirm it is 3 projects
    in the last 5 years
    
    ANSWER 3: 3 projects in the last 5 years is confirmed. RFP Annex
    A will be updated at the next opportunity.
    
    QUESTION 4: Solicitation amendment No 2 was published on MERX
    this week. Are there any changes from the original solicitation
    ? Aren't we at amendment No 005 ?
    
    ANSWER 4: The Solicitation is the 475 or so page document that
    includes Sol Parts 1 to 7, Annexes A and B, the SOWs, BOP, GFE,
    CHI and all related documents. The Solicitation itself (Parts 1
    to 7) has not changed, other than the closing time that was
    changed from 2:00PM EDST to 2:00PM EST (Sol amdt 001). Annexes A
    and B were updated this week (Sol amdt 002). 
    
    The Notice of Proposed Procurement (NPP) has been amended five
    times so far, to include Q&A No 1 to Q&A No 5. Canada can amend
    the NPP without amending the Solicitation.
    
    
    QUESTION 5: Schedule A para 4.4.7.3 Procurement identifies that
    "contractor shall use items from its own inventory for
    components that are common with other fleets in its service to
    the maximum extent possible."  Please advise how these items are
    to be invoiced under the Basis of Payment?
    
    ANSWER 5: As all DND-owned CC150 inventory is located in
    Trenton, segregated from any other fleet inventory, the
    Contractor is expected to replenish CC150 stock independently
    from its other business(es). Contractor would use items from its
    own inventory when doing heavy maintenance, component
    maintenance or engine maintenance, where applicable. The invoice
    for such maintenance would be based on time&material, with the
    time invoiced at the BOP hourly rate, and with materials
    invoiced at laid-down cost + the applicable mark-up of BOP Line
    item 5.0  
    
    QUESTION 6: In Appendix 3 Scoring Guide, Part B - Technical
    Point-Rated Requirements, PQA1, the Evaluation Criteria states
    "3 points will be given for the first DE and 2 points will be
    given for subs, up to a maximum of 5 points per specialty area".
    Please clarify how to achieve maximum points if all DEs are
    employed by the Prime (i.e. no subcontractors).
    
    ANSWER 6: Any bidder can achieve the maximum of 5 points per DE
    specialty area, should subcontractors be involved or not. Three
    points will be given for the first DE, and a maximum of 2 points
    will be given if there are additional DEs (substitutes). 
    
    
    QUESTION 7: In Part 3 - Bid Preparation Instructions: General,
    Paragraph 1.3 (a), the instruction states to "use 8.5 x 11 inch
    paper". Please confirm that it is acceptable to use larger paper
    by exception as fold-outs to illustrate complex schedules or
    charts for better readability.
    
    ANSWER 7: Canada confirms that larger paper format is authorized
    for fold-outs.
    
    
    QUESTION 8: In Appendix 3 Scoring Guide, Part B: Technical
    Point-Rated Requirements PMP3 and PQA3 both state 'Bidder is
    requested to list the personnel required on Table PQA3'. There
    is a table PQA2 in the RFP but no table PQA3. Please clarify if
    table PQA2 is the correct table to be used for the technical
    point-rated requirements PMP3 and PQA3. 
    
    ANSWER 8: Table PQA2 is the correct table to be used to list the
    personnel/qualifications for the point-rated requirements PMP3,
    PQA2 and PQA3, namely. However, Canada will accept any table
    labelled "PQA2", "PQA3" or "PQA2/PQA3" with a list of
    personnel/qualifications.
    
    
    Amendment No 005 is issued to provide a fifth Q&A.
    
    Question: As written, the SOW seems to impose the business model
    of Prime/Subs. Can a joint venture be considered as the Prime
    Contractor, with a clear division of responsibilities between
    the members of the joint venture? One of the partners in the
    joint venture would hold the AMO for line maintenance, and be
    responsible for the AMO-related requirements (MPM, quality
    program, etc). The other partner(s) would be responsible for
    contractual requirements, such as TSA, Training Systems, Point
    of Contact, reports, etc. 
    
    Answer:  A joint venture is authorized by Canada, as provided at
    clause 17 of the Standard Instructions 2003 (2012-07-11) that
    form part of the bid solicitation. Accordingly, the Prime
    Contractor can be a joint venture. However, if a contract is
    awarded to a joint venture, and as provided at clause 17 of the
    Standard Instructions 2003 (2012-07-11), the contract will
    provide that all members are jointly and severally or solidarily
    liable for the performance of the Work.
    
    	Also, certain requirements will have to be met by all members
    of a joint venture, such as security and financial solvancy
    matters. For other requirements, essentially technical in nature
    (AMO, parts distribution, etc.), the joint venture will need to
    demonstrate that at least one member meets these requirements.
    
    	Canada has revised the RFP documents to provide clear
    instructions with regards to the requirements that must be met
    by all members of the joint venture, or by at least one member.
    
    
    Amendment No 004 is issued to provide a fourth Q&A.
    
    Question 1. The bid preparation instructions indicate that 6
    copies of Document A (Technical Bid) are to be provided on
    CD-ROM.  Is it acceptable to provide these copies on a "flash
    drive", "memory stick" or "USB drive"?
    
    Answer 1. Yes. Bidders may provide their bid on a memory stick
    or other device that can be used with a laptop. Documents
    provided in .pdf format must have the OCR (Optical Character
    Recognition) feature. Microsoft Office Suite documents are
    accepted.
    
    
    Question 2. Tech SOW 4.3.1b) states that all interior and
    exterior cleaning services, though part of line maintenance
    services, may be sub-contracted. Are these services included in
    the firm monthly price, or can they be invoiced separately under
    BOP 3.1 c) (the second c) ?
    
    Answer 2. Interior and exterior cleaning services are included
    in the firm monthly price. During the site visit, 8 Wing showed
    bidders the hangar used for aircraft washing. Bidders were told
    that this facility was available to the CC150, and that the
    contractor's technicians would receive training. Bidders may
    however subcontract these services, but Canada will not pay for
    them under BOP 3.1 c)(2). 
    
    Sub-question a): Are NDT, machinist, etc., considered as AWR's ?
    (Ref: Sched A Paragraph 4.3.1 a), e) & f)
    Answer: a) Specialized services, such as machinist or NDT, could
    be considered as AWRs to line maintenance. They have in the past.
    Sub-question b): what is and/or was the average aircraft
    cleaning fee (interior and exterior) from the local
    subcontractor ?
    Answer: b) As these services are included in the line
    maintenance monthly price of BOP 3.1a), Canada does not know the
    average cost of aircraft cleaning. 
    
    Question 3. Please define "single entry" and "multiple entry" of
    BOP 3.1 c) (1).
    
    Answer 3. "Single entry" occurs when the CC150 lands in theatre
    once during a trip. "Multiple entry" occurs when the CC150 lands
    more than once, such as shuttling back and forth 3 times between
    Kandahar and Camp Mirage during the same trip. 
    
    Question 4. Reference SOW paragraph # 4.1.1 b and RFP Annex A,
    Appendix 3, Part A, Technical Mandatory Requirements, TM5, TM6,
    TM8 and TM9.  Are Bidders required to identity all service
    providers and submit copies of all specialized AMO certificates,
    and to submit copies of all MPMs to meet the mandatory
    requirement as stated?  Such a list could number in the hundreds.
    
    Answer 4. Canada will accept TC/FAA/EASA certificates for TM5
    and TM6. TM8 and TM9 are deleted. The program plan, transition
    plan and material management section of the scoring guide should
    describe how subcontractors will be selected IAW TC requirements
    (ie via bidder's existing MPM/MCM).  The bidder is not required
    to include TC manuals and certificates for each subcontractor. 
    There is no requirement to use only TC accredited organizations
    to perform component overhauls (ie outside Canada) since the
    CARs allows accepting foreign documentation.
    
    
    Question 5. The incumbent seems reluctant to assist DND with a
    smooth transition. Can you confirm the incumbent's contractual
    obligations on transition to the successful bidder?
    
    Answer 5. There was a misunderstanding during the site visit.
    The Contracting Authority told the attendants that the incumbent
    had not yet invoiced Canada for the cost of the license to
    SMART, which was not true. The invoice was on the incumbent's
    last claim that was sitting on her desk when she came back from
    Trenton. Bidders may ask any question about the IM/IT situation
    in order to prepare their bid. There are very little (if any)
    specific contractual obligations for the transition in the
    incumbent's contract.   
    
    
    Question 6. Can Canada provide a list of bidder attendees of the
    mandatory site visit ?
    
    Answer 6. A list will be provided to qualified bidders upon
    request. 
    
    
    Question 7: In reference to Tech SOW Clause 5.0, Customer
    Support and Other Services Agreements:
    
    a) Prior to bid award, does bidder need to provide documentation
    that it has communicated with Funkwerk (LOU or MOU) ?
    ANSWER: No. There is no requirement for the incoming contractor
    to enter a relationship with Funkwerk prior to bid award.
    
    b) Same question for AACS ? Is the cost also included in
    Miscellaneous Subcontracts of BOP 6.0 ? and if not, will that
    cost be paid by DND or does it need to be included in the Flat
    rate of Line Mtce ? 
    
    ANSWER: A letter of support from AACS, or a copy of existing CSA
    is required at RFP Annex A, Appendix 3, Scoring Guide. Tech SOW
    5.1.2 states that the "Prime Contractor shall enter a separate
    CSA with AACS as a Maintenance, Repair and Overhaul (MRO)
    organization for the purpose of buying products and services for
    the CC150." The cost of maintaining a MRO CSA with Airbus should
    be included in the flat rate of Line Maintenance. 
    
    c) In reference to Tech SOW 5.4 & 5.6 - Will these costs be paid
    by DND ? 
    ANSWER: Yes. These costs would be paid under BOP 6.0.
    
    
    Question 8: Can you confirm where the SMART data is hosted?
    Specifically, is it hosted on a DND server that bidder would
    gain access to on contract award, and presumably continue to use
    if desired; or, is it hosted on a L3 server that would require a
    different data transition strategy involving DND, L3 and the
    successful bidder?
    
    Answer 8: SMART is hosted on L-3 MAS server. As indicated in Q&A
    No 3, Canada will arrange for the transfer of CC150 specific
    data from L-3 MAS to the winning Bidder. The timeframe for this
    transfer is estimated to be within 30 days after contract
    termination. As indicated in Q&A No 2: Through the current
    In-Service Support contractor L-3 MAS, Canada has acquired a
    license to SMART and secured the services of engineer Yong Li to
    support the application at a cost of $3,000./month. SMART will
    be made available to the next In-Service Support contractor by
    DND. There is no interface between SMART and SAP, the IM/IT
    application used by L-3 MAS, nor with any DND system or
    application, nor with any other application. 
    
    Question 9: Is it mandatory to have DAO/AEO qualifications in
    order to respond to the RFP or can this be subcontracted? Would
    this penalize the bidder in any way? 
    
    Answer 9.: Sub-contracting of the DAO/AEO is allowed and it
    should not penalize the bidder. However, bidder is requested to
    provide a firm fixed monthly rate for the engineering support as
    well as an hourly rate for Additional Work Requests. Further,
    bidders are requested to provide a list of engineers with
    qualifications and delegations. Bidders are referred to
    Evaluation criteria PQA1 where a delegation matrix and letter of
    support from the subcontrator is called for.
    
    
    Question 10: Are the Material Management, 3 buyers, A/C record
    clerks and Admin support still located in YYZ ?  If yes, what is
    the square footage used ?
    
    Answer 10: L-3 MAS relocated the Material Management team from
    Air Canada-owned offices to L-3 Communications-owned offices in
    Toronto. No information on square footage is available.
    
    
    
    Amendment No 003 is issued to provide a third Q&A, and to amend
    the closing time to 2:00PM EST on 20-12-2012. The closing time
    of the Solicitation, as well as Annex B, Instructions for
    Financial Proposal Submission, were updated. A summary of the
    mandatory site visit and a copy of the 437 Sqn Powerpoint
    presentation are available upon request to the Contracting
    Authority. 
    
    QUESTION 1. Does the transfer of data from Smart and SAP (both
    at L-3 MAS) into another database need to be done prior to the
    first Heavy check ? What would be the timeframe to transfer the
    data? What cooperation can we expect from L-3 MAS?
    
    ANSWER 1: Canada will arrange for the transfer of CC150 specific
    data from L-3 MAS to the winning Bidder. The timeframe for this
    transfer is estimated to be within 30 days after contract
    termination.  As the Start of Service date is unknown, the first
    Heavy check could be performed at Avianor or EADS EFW.
    
    QUESTION 2. What is the format of the data to be transferred ? 
    		            
    ANSWER 2: Data in SMART is in a SQL database.  Bidders are to
    explain, as part of their transition plan, activities and
    timeframe for migrating data and for set-up of their proposed
    IM/IT solution.  
    
    QUESTION 3. Will  there be a cost associated to acquiring the
    data from L-3 MAS that bidders need to take into consideration
    in their price proposal?
    		 
    ANSWER 3: Canada would pay for any cost associated to the
    close-out of the contract with L-3 MAS directly. Bidders need
    not consider them. 
    
    QUESTION 4. Schedule C, Tables 1 & 2: 30,000 hours are estimated
    for the heavy Mtce. Is this the number that needs to be used for
    the bid ? Is there a flat rate portion and AWRs invoiced on a
    Time and Material basis?
    				
    ANSWER 4.: In the performance of the work, there could be a flat
    rate portion and additional work invoiced on a T&M basis. For
    bid evaluation purposes, estimated total hours were provided to
    bidders. Some checks are heavier than others, and Canada does
    not wish to provide specific details in the RFP. 
    	
    QUESTION 5. Does the following estimated subcontracting need to
    be included in the Canadian portion 80% and foreigner 20% ?
    a.       300k $ for EADS
    b.      Component repairs
    c.       Aircraft painting
    				
    ANSWER 5.: The total bid price for the service will be
    established from Table 2 of the Proposed Basis of Payment. The
    cost associated to these subcontracts is excluded from the
    calculation. A bidder who would subcontract the heavy
    maintenance outside Canada might not meet the 80% Canadian
    content.
    	
    QUESTION 6. Who decides what modifications (not included in the
    Capital projects, TA or DND626) or SB are nice to have and are
    to be embodied on the CC150 fleet ?
    				
    ANSWER 6.:  The Technical Authority makes that decision based on
    the recommendations of the ISS contractor.
    	
    QUESTION 7. In appendix 3, annex 1 (Line Mtce), what would be
    considered as additional work request (AWR) ? There is already a
     flat rate for the labour which includes the A check, deployment
    operations, MRP, management, etc. 
    				
    ANSWER 7.: In the past, DND has paid for additional work
    performed by specialized technicians (machinists for example)
    dispatched from other Aveos or Air Canada bases. There are very
    little AWRs related to Line Maintenance. Most of the overtime
    hours are mission related. 
    
    QUESTION 8. On page 1 of the Final RFP released 22 October ,
    please confirm the closing time should read 02:00 PM Eastern
    Standard Time, not Eastern Daylight Saving Time?.
    
    ANSWER 8.: Closing time is EST. The Solicitation will be amended.
    
    QUESTION 9. RFP, Schedule A, SOW, 2.2 Ground Interruptions:
    Please confirm this should address only flight dispatch delays
    greater than 15 minutes due to technical cause factors within
    the Contractor's control and responsibility.  A failure in the
    airfield lighting system, for example, is a technical factor not
    under the Contractor's control and responsibility.
    
    ANSWER 9.: SOW 2.4 and 2.5 exclude interruptions caused by
    factors outside of the contractor's control.
    	
    QUESTION 10. The CC150 ISSC SOW includes work performed under
    support contracts (Trend Monitoring with GE, Tech data and pubs
    with Airbus, RTOWLs with Aviatec, Training systems with
    Funkwerk). Without the individual SOWs for these Customer
    Service Agreements, it is impossible to price CC150 ISSC SOW
    work elements and avoid duplication with existing DND funded
    agreements. 
    
    ANSWER 10.: Canada entered into agreements with GE, Aviatec and
    Airbus. The incumbent entered into an agreement with Funkwerk.
    The cost associated to Funkwerk is included in the Miscellaneous
    Subcontracts of BOP 6.0.  SOW 5.0 describes the work required
    from the ISS contractor. 
    
    
    QUESTION 11. How will IM/IT transition costs be compared between
    incumbent and other bidders? The incumbent will have a lower
    price. Also, it is not clear where IM/IT long term sustainment
    costs are to be priced. Is it to be assumed that IM/IT price is
    included in the burdener rate for BOP Line Item 3.1a? Could a
    separate BOP Line Item be provided?
    
    ANSWER 11.: Bidders will need to figure their cost to transfer
    the data from the systems used by L-3 MAS into their own. That
    would be part of the bidder's transition cost. The incumbent
    should have lower transition costs, for having won the last
    competition. All bidders will need to figure their IM/IT costs,
    including long term sustainment. No separate line item will be
    provided in the BOP. The cost to provide IM/IT services in
    Trenton should be part of the Line Maintenance Support monthly
    fee, that for engineering services should be part of the
    Engineering Support monthly fee, and the same goes for Material
    Management. Bidders are reminded that DND does not provide any
    office equipment: desks, computers, printers, photocopiers,
    etc., as well as related services are provided by the Contractor.
    
    
    QUESTION 12. Is it to be assumed that the price for recurring
    and regenerative training after transition is included in the
    burdened rate for BOP Line Item 3.1a? Could a separate BOP Line
    Item be provided?
    
    ANSWER 12.: Canada does not pay for training costs. Initial
    training, recurrent training, training of new employees, etc.,
    are costs borne by the Contrator. Initial training should be
    part of the transition cost, and the rest would be included in
    your montly fees.
    
    
    
    Amendment No 002 was issued to provide a second Q&A. 
    
    QUESTION 1. Do bidder's pro rate a transition plan from a
    baseline of an accredited ERKS or from a non-accredited RKS? 
    
    ANSWER 1: DND does not baseline the transition plan evaluation
    against having or not having an existing accredited Record
    Keeping System (RKS).  DND will evaluate if the transition plan
    adequately describes the activities required to move the
    technical records from SAP to a new system.  Since this is a
    complex task, DND expects the contractor to be explicit on the
    activities required to perform this transition, i.e. covering
    the activities in the TAA ERKS advisory.  DTAES RKS specialists
    will evaluate this plan, including feasibility and estimated
    timeline for implementation.  
    
    
    QUESTION 2. Can DND confirm their expectation for support to
    deployed operations?  The RFP provides a manpower simulation
    that indicates DND expects 12 technicians per MRTT deployment. 
    However, this conflict with what the operational squadron
    predicts.
    
    ANSWER 2. The fourth bullet in the Notes of Table PMP3 is
    replaced by the following: DND's requirement is a minimum crew
    of 3 qualified technicians (ACAs) per refueler on air-to-air
    missions, available 24/7, and a permanent state of readiness.
    DND's expectation is sufficient resources to sustain long term
    deployments and Northern operations, with minimal impact on home
    base (Trenton) operations. 
    
    QUESTION 3. With respect to the current maintenance support tool
    "SMART", who owns the IP/licensing and what support contract are
    in place to provide ongoing updates?  In addition, what
    interfaces exist between SMART and the L3 MAS/ and DND DRMIS
    that will require data inputs to DND or other support
    contractors (i.e., Airbus)?
    
    ANSWER 3. Through the current In-Service Support contractor L-3
    MAS, Canada has acquired a license to SMART and secured the
    services of engineer Yong Li to support the application at a
    cost of $3,000./month. SMART will be made available to the next
    In-Service Support contractor by DND. There is no interface
    between SMART and SAP, the IM/IT application used by L-3 MAS,
    nor with any DND system or application, nor with any other
    application. 
    
    QUESTION 4. What is the office square footage for 32 Buffalo? Do
    we have the general sqf allocated for CC150 operations in 6
    hangar? 
    
    ANSWER 4. Bidders are invited to contact the Contracting
    Authority named below for a copy of the drawing.
    
    QUESTION 5. Will the presentations during the CC150 Bidder's
    Conference be made available?
    
    ANSWER 5. A copy of the 437 Sqn Powerpoint presentation is
    available upon request to the Contracting Authority.
    
    
    Amendment No 001 was issued to provide additional information
    and directions for the mandatory site visit at 8 Wing Trenton on
    06 November 2012. A first Q&A was also provided.
    
    Q&A #1:
    
    QUESTION:  Is provision of a certified (TAA accepted) ERKS
    mandatory? If not, is DID AW-002 required with the Proposal?
    
    ANSWER:  The intended wording in the SOW was to avoid forcing a
    specific technical record keeping solution on the bidder that
    may hinder the bidder's performance, perhaps due to an existing
    efficient paper based system.  If the bidder elects to use a
    100% paper solution, they shall describe this solution within a
    separate plan to meet TM15, and the TAA advisory 2007-01 will no
    longer apply.  Bidders should also not take for granted what
    constitutes an ERKS.  For example, a simple solution using excel
    spreadsheet for, but not limited to tracking aircraft
    maintenance lives, inspection forecasting, and electronic
    component history records, would all invoke TAA advisory
    2007-01.  If the bidder proposed a hybrid paper/ERKS solution
    and did not draft a project plan in accordance with TAA advisory
    2007-01, they would not meet TM15 and therefore be
    non-compliant.  The bidder should also be aware of the other
    rated criteria, particularly IMIT and CM.  Using a 100% paper
    technical record solution may make it difficult for the bidder
    to meet the minimum score of 12 in each category and therefore
    be non-compliant.  One would also expect using a paper based
    system to require more staff, thus TP2 should reflect this. The
    Authorities also wish to point out that the incumbent is
    implementing an ERKS. The bidder's transition plan will need to
    address how they will transition from L-3 MAS' electronic system
    to a paper system.
    
    
    ORIGINAL NPP:
    
    The Department of National Defence (DND) requires in-service
    support for the CC150 Polaris aircraft (Airbus A310-304) for 8
    Wing Trenton, Ontario. Activities include servicing, repair and
    overhaul of the aircraft and related equipment using a
    commercial approach. In the performance of the work, the
    contractor shall supply, other than Government Issue, all the
    resources, facilities, labour and supervision, management
    services, equipment, materials, drawings, technical data,
    technical assistance, engineering services, inspection and
    quality assurance procedures and planning necessary to perform
    the work as specified in the Statement of Work and related
    documents.
    
    The period of service is five (5) years, from contract award to
    31 March 2018, with two option periods of five (5) years each,
    up to 31 March 2028.
    
    Any contract resulting from the Request for Proposal (RFP) is a
    replacement for an existing contract.  Included with this RFP is
    a requirement for continuity of service which must be addressed
    by providing a Transitional Service Plan.
    
    This procurement includes a mandatory site visit at 8 Wing
    Trenton on 06 November 2012. For more information, consult RFP
    Part 2, Section 6.
    
    This solicitation is solely limited to Canadian suppliers.
    
    There are security requirements associated to this procurement: 
    
    - Before award of a contract, the Contractor must hold a valid
    Facility Security Clearance at the level of SECRET, issued by
    the Canadian Industrial Security Directorate (CISD), Public
    Works and Government Services Canada (PWGSC);
    
    - The Contractor personnel requiring access to CLASSIFIED
    information, assets or sensitive work site(s) must be citizens
    of Canada and must EACH hold a valid personnel security
    screening at the level of SECRET.
    
    For more information on the security requirements, consult RFP
    Part 6.
     
    Any questions regarding this requirement should be directed to:
    
    Lorraine Chauvin
    Supply Specialist
    PWGSC
    Place du Portage, Phase III,  Tower C, 
    11 Laurier Street,
    Gatineau, Quebec 
    K1A 0S5 
    Tel: (819) 956-0559,  Fax: (819) 956-9110
    Email address: lorraine.chauvin@tpsgc-pwgsc.gc.ca
    
    
    
    Delivery Date: Above-mentioned
    
    The Crown retains the right to negotiate with suppliers on any
    procurement.
    
    Documents may be submitted in either official language of Canada.

    Contract duration

    Refer to the description above for full details.

    Trade agreements

    • No trade agreements are applicable to this solicitation process

    Partner with another business

    The functionality to add your company name to the list of interested businesses is temporarily unavailable.

    This list does not replace or affect the tendering procedures for this procurement process. Businesses are still required to respond to bid solicitations, and to compete based on the set criteria. For more information please read the Terms of use.

    Contact information

    Contracting organization

    Organization
    Public Works and Government Services Canada
    Address
    11 Laurier St, Phase III, Place du Portage
    Gatineau, Quebec, K1A 0S5
    Canada
    Contracting authority
    Chauvin, Lorraine
    Phone
    (819) 956-0559 ( )
    Fax
    (819) 997-0437
    Address
    11 Laurier St. / 11, rue Laurier
    8C1, Place du Portage
    Gatineau, Québec, K1A 0S5

    Buying organization(s)

    Organization
    Department of National Defence
    Address
    101 Colonel By Dr
    Ottawa, Ontario, K1A0K2
    Canada
    Bidding details

    Full details regarding this tender opportunity are available in the documents below. Click on the document name to download the file. Contact the contracting officer if you have any questions regarding these documents.

    Access the Getting started page for details on how to bid, and more.

    Eligibility and terms and conditions

    Government of Canada tender and awards notices, solicitation documents, and other attachments are fully accessible and available free of charge and without having to register on CanadaBuys.

    Information may be available on another source prior to being available on CanadaBuys. You may have received this information through a third-party distributor. The Government of Canada is not responsible for any tender notices and/or related documents and attachments not accessed directly from CanadaBuys.canada.ca.

    Government of Canada tender or award notices carry an OpenGovernment License - Canada that governs its use. Related solicitation documents and/or tender attachments are copyright protected. Please refer to our terms and conditions page for more information.

    Summary information

    Notice type
    Request for Proposal
    Language(s)
    English, French
    Region(s) of delivery
    Ontario (except NCR)

    Support for small and medium businesses

    If you have questions about this tender opportunity, please contact the contracting officer, whose information is found in the Contact information tab. 

    Refer to our Support page if you need help or have questions about the government procurement process, including how to bid or how to register in SAP Ariba. You can also contact Procurement Assistance Canada, which has offices across Canada.

     

    Date modified: